This project is a bridge across Shuren 3rd street retention pond; approximately 115 meters in length (including 30 meters water passage and 20 meters right-of-way).The design concept of the bridge and the overall landscape is based on "the retention pond landscape with a low-profile span bridge ". Thus, the bridge-type adopts three-span continuous steel I-beam bridge was constructed in retention pond and minimum scour design.
The project has completed in December, and commencement ceremony hold on December 23, 2020.
【Awards】
The 14th Golden Safety Award of public works.
Client: Taoyuan City Government Office of Public Construction Length of Bridge: 115 meters approximately Construction Fees: NT$ 151,111,100 Location: Taoyuan District, Taoyuan City Dates: 2019.03.30~2020.12.21
Founder
Company Profile
Organization Chart
Philosophy
Group Distribution
Certification
Awards
Bridge / Viaduct
Freeway / Highway
High Speed Rail / Railway
Mass Rapid Transit
Airport
Building Structures
Land Development
Construction Management / Supervision
Environmental Engineering
Water Resources / Soil Conservation
Landscape Engineering / Landscap Lighting
Inspection / Evaluation & Retrofit
Urban Planning
BIM(Building Information Modeling)